Sequencing test methods so a novel binder either clears into production or fails early enough to allow a substitution before schedule is at risk.

Project schedule and cost comparison: industry-baseline trial-mix workflow vs LOGiMIX A two-panel gantt chart comparing the industry-baseline trial-mix workflow (three trial batches over 19 weeks) against the LOGiMIX workflow (single confirmation batch over 10 weeks), with a cumulative cost band underneath each panel and a modeled-savings callout showing approximately nine weeks faster and lower iteration cost. PROJECT SCHEDULE & COST COMPARISON Industry-baseline trial-mix workflow — ~$15k total iteration cost Phase 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Mix design + sourcing Trial batch 1 Trial batch 2 Trial batch 3 Commercial pour QC break (7d / 28d) Cumulative $ ▶ $5k $10k $15k With LOGiMIX, Standard tier — ~$5.5k total iteration cost Phase 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 LOGiMIX report (Std) Confirmation batch Commercial pour QC break (7d / 28d) Cumulative $ ▶ $499 $5.5k ★ Modeled savings: ~9 weeks faster, ~$9.5k lower iteration cost Cumulative cost legend: $0-5k $5-10k $10-15k $15-20k $20k+ SUNNYDAY TECHNOLOGIES · CONSULTING CASE EXAMPLE

The situation

A developer was preparing to introduce a calcined-clay binder system on a regional infrastructure pour with state-DOT proximity. The applicable test methods spanned ASTM, AASHTO, and F42 process specifications, and the overlap was not obvious to the developer’s project manager. A less-disciplined methodology would have triggered redundant testing and a calendar slip the project schedule could not absorb.

The work

A mapping of the applicable test methods across ASTM, AASHTO, and F42. A sequenced qualification plan with gating criteria at each stage, so a failure early in the sequence would trigger a substitution decision before the developer was committed to a binder that could not clear DOT review. The standardized schedule-and-cost comparison shown above, anchored to the industry-baseline trial-mix workflow, is the format we use to communicate the plan to a developer’s project manager.

The outcome

The qualification calendar shortened against the industry-baseline trial-mix workflow. The avoided-iteration line was material against the project’s lab budget. The developer’s project manager now uses the same sequencing template, and the comparison chart, for any new binder system entering the company’s project pipeline.


This page describes a composite of common consulting work and does not refer to a specific past customer, project, or engagement terms. Outcomes vary considerably with project specifics and are not guaranteed. Sunnyday Technologies provides technical analysis. Sunnyday Technologies does not provide professional engineering, legal, regulatory, or financial advice. Engineering sign-off on any specific project remains the responsibility of the licensed engineer of record.